- Objects: factories of the scales falling under type 2 designated energy management factory Fuel = 1,500 to 3,000kL/y, electric power = 6 to 12 million kWh/y
- Audit to be done in response to application by the audited factory
- Submission of the preliminary survey sheet on energy audit from the applicant
- One-day onsite survey by two specialists, one in thermal energy and the other in electric power
- Analysis of data and sending of the report
- Energy audit done free of charge (administration’s budget)
- Nationwide endeavor (at ECCJ’s 9 branches)
- Items to be entered are standardized and statistical analysis is facilitated.
- The audited factory has no obligation to implement the proposals.
- Questionnaire surveys one year after audit indicate that about 30 percent of the proposals are implemented.
- Specialists are selected from those who have been registered in ECCJ.
- The institution and procedure of energy conservation audit for buildings are the same as those of the factory energy conservation audit.
|