Outline of the system
* Objects: factories of the scales falling
under type 2 designated energy management
factory
Fuel = 1,500 to 3,000kL/y, electric power
= 6 to 12 million kWh/y
* Audit to be done in response to application
by the auditee factory
* Submission of the preliminary survey sheet
on energy audit from the applicant
* One-day onsite survey by two specialists,
one in thermal energy and the other in electric
power
* Analysis of data and sending of the report
* Energy audit done free of charge (administration's
budget)
* Nationwide endeavor (at ECCJ's 9
branches)
* Items to be entered are standardized and
statistical analysis is facilitated.
* The auditee factory has no obligation to
implement the proposals.
* Questionnaire surveys one year after audit
indicate that about 30 percent of the proposals
are implemented.
* Specialists are selected from those who
have been registered in ECCJ.
* The institution and procedure of
energy
conservation audit are the same as
those
of the factory energy conservation
audit.
|