Outline of the system
* Objects: factories of the scales falling
under type 2 designated energy
management
factory
* Fuel = 1,500 to 3,000kL/y,
electric power
= 6 to 12 million kWh/y
* Audit to be done in response
to application
by the auditee factory
* Submission of the preliminary
survey sheet
on energy audit from the applicant
* One-day onsite survey by two
specialists,
one in thermal energy and the
other in electric
power
* Analysis of data and sending
of the report
* Energy audit done free of charge
(administration's
budget)
* Nationwide endeavor (at ECCJ's
9 branches)
* Items to be entered are standardized
and
statistical analysis is facilitated.
* The auditee factory has no
obligation to
implement the proposals.
* Questionnaire surveys one year
after audit
indicate that about 30 percent
of the proposals
are implemented.
* Specialists are selected from
those who
have been registered in ECCJ.
* The institution and procedure
of energy
conservation audit are the same
as those
of the factory energy conservation
audit.
|
|