3. Lower the Pressure Setting (1st Sec., 2nd Sec.)
Check the specifications of equipment again. All required less than 0.5 Mpa supply pressure.
Lower the pressure setting by 0.05 Mpa in phases, once in a week
At the same time, air leakage was identified and repaired in the 1st Sec. as in the 2nd Sec.
Air leakage was reduced to
0.1 m
3
from
7.2 m
3
.