ENERGY AUDITS IN INDUSTRIAL PLANTS
Energy Audit's Steps
  • Visit to the Factory
    one or two member of energy audit team visit to the Factory;
    - in order to determine the size of Factory,
    - to have visual understanding of the departments of the Factory,
    - to determine the necessary portable test equipment which are to be used in audit areas,
    - to determine (and show to the factory staff) the locations which test equipment are to be installed,
    - to determine the suitable time for audit and duration and work schedule of audit,
    - to clearify the some information on the received questionnaire,

ENERGY AUDITS IN INDUSTRIAL PLANTS
Energy Audit's Steps
  1. Pre - Audit
    According the result of factory visit, energy audit team, (four or five engineers from different disciplines) go to the factory for pre-audit at the pre-determined date.
    Pre - Audit can be completed in two days in small and medium size factories. In big factories can be one week.