Energy Audit's Steps

  1. Detailed Audit
    Like pre-audit, energy audit team, (four or five engineers from different disciplines) go to the factory for detailed audit at the pre-determined date.
    Detailed Audit can be completed in a couple weeks or longer.
    Normally detailed audit is conducted after completion of pre-audit. However detailed audit can be done as completely independent from pre-audit.

ENERGY AUDITS IN INDUSTRIAL PLANTS
Energy Audit's Steps

  1. Detailed Audit
    During this time measuring equipment are installed in pre determined locations and measurement are made during a period of a couple of days under the actual operating conditions.