AEEC Home | Training Index | Index | Top | Previous | Next |
METI/ECCJ/AOTS Training Program | Vietnam |
Breakdown of Combined Order Value by Type of Contract (ESCO Projects) |
![]() Jun. 2004, Survey of Japan Association of Energy Service Companies (membership 107 companies) |
ESCO Project Example (city hotel) |
||||||||||||||||||||||
1. Name of example ANA Hotel Tokyo Energy Conservation Retrofitting 2. ESCO Yamatake Building System Co., Ltd. 3. Facility overview
(ESCO 2004-8) |
ESCO Project Example (city hotel) cont'd |
5. Finance Self-financing |
ESCO Project Example (city hotel) cont'd |
11. Energy conservation equipment used ![]() |
ESCO Project Example (city hotel) cont'd |
12. Energy savings achieved
Energy consumption before ESCO project 388,669 GJ/year Energy consumption after ESCO project 307,921 GJ/year Reduction in energy consumption 80,748 GJ/year (20.8% reduction) ![]() |
13/13 Next |
AEEC Home | Training Index | Index | Top | Previous | Next |
Copyright(C) ECCJ 1996-2019 |