(1) Management of power receivers, transformers and distributors
1) Maintain adequate demand level for transformers, etc.
2) Optimize the placement of power receivers and transformers, shorten power
distribution route and optimize voltage.
3) Power factor of power receiving end is 90% or above, and improve it by installing
phase advance capacitors using the separate Table 4 as "reference".
4) Manage phase advance capacitors to be started and stopped in a way that fits the
equipment they are installed.
5) If single phase load is connected to 3-phases, manage it in a way that prevents
uneven voltage.
6) To operate electric equipment, decrease maximum current by making the use of
electricity even.
7) Reduce electric loss of power receivers, transformers, distributors, etc. |